HOME > PV Blog > Four new schemes to start in Japan in FY 2023 – Key point 2

Four new schemes to start in Japan in FY 2023 – Key point 3

2023.03.09
Regulations/Initiatives
Japan Solar Update: No.35  (Mar 6 ~10, 2023) 
benchmark

<Key points 3>

  • Applications for non-firm type connections to the local grid will be accepted from April 1, 2023
  • Non-firm type connections will be applied uniformly regardless of the availability of capacity on the local grid
  • Output curtailment for congested grids will be based on S+3E merit order and follow the order and the method of output curtailment by re-dispatching method (of a certain order)

 

 

Non-firm connections to the local grid      Acceptance of applications starts on April 1, 2023

 

Non-firm type connections will be applied uniformly regardless of the availability of capacity on the local grid.

 

Coverage and a method of output curtailment needed when the grid is congested

  • It is appropriate to treat congestion by merit order considering S+3E even in local grids which have fewer dispatchable power sources (thermal power, etc.) and more renewable energy connections than bulk power systems
  • The order and the method of output curtailment will basically follow the re-dispatching method (of a certain order) the same as those for bulk power systems

 

Rules of output curtailment based on re-dispatching method (of a certain order)

 

Curtailment

Non-firm connections are applied on a trial basis in the Tokyo area ahead of others, and grid congestion may occur from FY 2024

 

Publication and disclosure of grid information

  • It is important to increase predictability of output curtailment due to grid congestion
  • Information will be published/disclosed on the same items as for the bulk systems in principle, with correspondence based on the characteristics of the local grid

 

Supply capacity and handling of various markets

Capacity market Non-firm power sources can also participate in main auctions of the capacity market for the actual supply and demand of FY 2027.

Supply-demand adjustment market

Non-firm power sources can also participate in the supply-demand adjustment market for the time being (until about FY 2026).

 

 

Figure 3 Summary of the non-firm connection to local grids Source: Materials of the Subcommittee for Large-volume Introduction of Renewable Energy and Next Generation Electricity Network, compiled by RTS Corporation

Please contact us

CONTACT

Please contact us from the inquiry form.