emailContact file_downloadDownloads
JP EN

RTS Corporation

PV Blog

HOME > PV Blog > Japan to Introduce Upper Limits on Grid Connection Assessments for Battery Storage Projects

Japan to Introduce Upper Limits on Grid Connection Assessments for Battery Storage Projects

2026.05.28
Regulations/Initiatives
Japan Solar Update: No.202 (May 25 ~ 29, 2026)

 

Before the operation of the upper limit setting begins, there is a possibility that there will be a rush to apply for connection consideration.

 

<Key points>

  • Regarding grid-scale storage batteries, the upper limit of the number of connection assessments per operator will be applied from August 1, 2026, and if the applications have been accepted as of July 31, 2026, the response will be as before
  • If the number of applications exceeds the upper limit, the general power transmission and distribution operators will not check the application documents, and after the upper limit is resolved, the grid connection applicants will be asked to apply again for connection assessment
  • The specific upper limit is being calculated, but the results of the calculation of the upper limit in each area were presented as a reference

 

 

Response to rapid grid connection of power generation facilities including grid storage batteries

When to start setting the upper limit on the number of connections considered per operator

    • Relevant regulations of the OCCTO will be revised, which will be applied from August 1, 2026
    • If the number of applications exceeds the upper limit as of July 31, 2026, the response will be the same as before
    • The upper limit will be applied to projects that were applied before August 1 but have not been accepted as of August 1
    • The specific upper limit is being calculated by general transmission and distribution companies, and will be published on each operator’s website as soon as the calculation is completed

Handling of applications exceeding the upper limit

If the applications exceeds the upper limit, the general transmission and distribution company will not check the application documents, and after the upper limit is resolved, the applicants will be asked to apply again for connection assessment

 

Estimates of the upper limit (reference)

Set the upper limit to the average value +2σ or the lowest value of 5 cases, whichever is higher

Area Actual Fiscal Year of Use Average+2σ* Upper Limit*
Hokkaido FY 2023 4 5
Tohoku FY 2023 6 6
Tokyo FY 2023 11 11
Chubu FY 2023 4 5
Hokuriku FY 2023 8 8
Kansai FY 2023 10 10
Chugoku FY 2023 4 5
Shikoku FY 2023 4 5
Kyushu FY 2023 8 8
Okinawa –  –  – 

 

* Based on estimates as of March 2026 and may differ from the actual upper limits to be applied

Figure 1 Summary of deliberations related to setting of the upper limit of the number of connection assessments per operator

Source: Materials of the 10th meeting of the Working Group on the Next-Generation Electric Grid, complied by RTS Corporation

Please contact us

CONTACT

Please contact us from the inquiry form.